PortService PST
LiveUtility token that gives investors priority access, discounts on port services, and potential high ROI due to the successful operation of the universal transshipment complex in the port of Chornomorsk.
Ends in
Platform
Origin
Price
Soft cap
Hard cap
KYC
Restricted countries
Buy with
Contract Address
Total Supply
Total Valuation
Project Description
Roadmap
-
2025 Q3–Q4
Foundation Phase
Description: Launch of the strategic project to build the Universal Transshipment Complex at Chornomorsk port. Geodetic and engineering surveys Design and cost-estimate documentation Obtaining permits Procurement of equipment and materials for foundation works Construction of pile field, concrete pouring, preparation for vertical construction Outcome: Terminal foundation fully laid Project moves to vertical phase (structure assembly) Foundation prepared for port infrastructure
-
2026 Q1
Consolidation Phase
Description: Monitoring and instrumental testing of the laid foundation Reinforcement and optimization of drainage systems Construction of temporary roads, storage and ramp areas Installation of basic infrastructure (power and water) for structure assembly Outcome: Foundation verified and reinforced to standards Infrastructure prepared for metal structure assembly
-
2027 Q1
Structural Phase
Description: Installation of quay metal structures Construction of warehouses, hangars, canopies Installation of cranes, mobile unloaders Electrification and installation of supports Start of office and technical infrastructure setup Outcome: Functional buildings and handling capacities created Ready for supporting infrastructure deployment: roads, logistics, security
-
2028 Q1
Commissioning Phase
Description: Completion of auxiliary and service structures Testing and certification of cranes and lifting equipment Setup of safety and operational control systems Commissioning works on power and networking substations Outcome: All key structures are operational and certified Ready for large-scale logistics system integration
-
2029 Q1
Infrastructure Phase
Description: Installation of railway tracks and access roads Integration with national logistics system Installation of IT infrastructure, surveillance, cargo automation Construction of customs and control zones Paving, marking, lighting Outcome: Complex connected to national logistics Cargo management, technical control, and safety systems implemented
-
2030 Q1
Integration Phase
Description: Full integration of IT and SCADA systems into unified management platform Automation of customs and security procedures Optimization of road and rail transport flows Deployment of mobile applications for cargo tracking Outcome: Infrastructure operates in a single information space Maximum transparency and speed of logistics operations
-
2031 Q1
Launch & Operation Phase
Description: Certification, state inspections, test cargo handling Setting up operational model: CRM, ERP, customs processes Forming partnership agreements with logistics companies Public launch (Grand Opening) Launching bonus program for token holders (discounts, priority service) Marketing and partnership campaigns to attract new partners Liquidity support mechanisms and cooperation with strategic investors Listing on major DEX/CEX: integration with decentralized and centralized exchanges Trading campaigns and market activity stimulation Outcome: Terminal receives first cargoes PST holders gain utility benefits: Priority access, unloading discounts, investor dashboard access, extended partner network, stable market and token liquidity growth
-
2032 Q1
Expansion Phase
Description: Expansion of service offerings (express handling, additional services) PST token listing on new exchanges and liquidity platforms Market-making mechanisms to support price and trading volume Active engagement of strategic partners and clients Outcome: Stable growth in handling volumes and PST trading Expanded ecosystem of partners and users